- precedence diagramming
- precedence diagramming
An activity oriented system in which activities are displayed in uniform boxes
complete with activity number, start duration and finish dates. The logical
relation between activity boxes is shown by logic connector lines. Lead and lag
times can also be shown. The display is more effective than Arrow Diagramming
and is also easier to revise, update, and program on computer. See also CPM and
PERT.
Source: Max Wideman.com
Copyright: Wideman Comparative Glossary
of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March
2002.