- definitive estimate
- definitive estimate
(Accuracy -5, +10 Percent) A definitive estimate is prepared from well defined
data, specifications, drawings, etc. This category covers all estimate ranges
from a minimum to maximum definitive type. These estimates are used for bid
proposals, bid evaluations, contract changes, extra work, legal claims, permit
and government approvals. Other terms associated with a Definitive Estimate
include check, lump sum, tender, post contract changes. etc.
Source: Max Wideman.com
Copyright: Wideman Comparative Glossary
of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March
2002.