- relaties tussen activiteiten
- dependencies
Logische samenhang tussen activiteiten. Er zijn vier typen relaties mogelijk:
1. Finish-to-start-relatie (FS);
2. Start-to-start-relatie(SS);
3. Finish-to-finish-relatie (FF) en
4. Start-to-finish-relatie (SF).
De benaming van de typen geeft eerst de begin- of einddatum van de voorlopende activiteit, gevolgd door de begin- of einddatum van de vervolgactiviteit.
Bron: Kennisconsult
Relationships between products or tasks. For example, one product may be made up
of several other 'dependent' products or a task may not begin until a
'dependent' task is complete.
Source: Max Wideman.com
Copyright: Wideman Comparative Glossary
of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March
2002.
A dependency between two project activities, or between a project activity and a
milestone. See also precedence relationship. The four possible types of logical
relationships are:
- Finish-to-start: the "from" activity must finish before the "to" activity
can start.
- Finish-to-finish: the "from" activity must finish before the "to" activity
can finish.
- Start-to-start: the "from" activity must start before the "to" activity can
start.
- Start-to-finish: the "from" activity must start before the "to" activity can
finish.
Source: Max Wideman.com
Copyright: Wideman Comparative Glossary
of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March
2002.