- progress line
- progress line
A visual representation of the progress of a project, displayed on the Gantt
Chart. For a given progress date, the progress line connects in-progress tasks,
thereby creating a graph on the Gantt Chart with peaks pointing to the left for
work that is behind schedule and peaks pointing to the right for work that is
ahead of schedule. The distance of a peak from the vertical line indicates the
degree to which the task is ahead of or behind schedule at the progress date.
Source: Max Wideman.com
Copyright: Wideman Comparative Glossary
of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March
2002.