- performance measurement baseline
- performance measurement baseline
The time-phased budget plan against which project performance is measured. It is
formed by the budgets assigned to scheduled cost accounts and the applicable
indirect budgets. For future effort, not planned to the cost account level, the
Performance Measurement Baseline also includes budgets assigned to higher-level
CWBS elements. The PMB does not include any management or contingency reserves,
which are isolated above the PMB.
Source: Max Wideman.com
Copyright: Wideman Comparative Glossary
of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March
2002.