logisch verband

 - logisch verband
 - logical relationship
 - relation logique
 - logische Beziehung


A dependency between two project activities, or between a project activity and a milestone. See also precedence relationship. The four possible types of logical relationships are:
- Finish-to-start: the "from" activity must finish before the "to" activity can start.
- Finish-to-finish: the "from" activity must finish before the "to" activity can finish.
- Start-to-start: the "from" activity must start before the "to" activity can start.
- Start-to-finish: the "from" activity must start before the "to" activity can finish.
Source: Max Wideman.com
Copyright: Wideman Comparative Glossary of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March 2002.

Kennisconsult
Laatst bijgewerkt: 23-01-2018
Thema: *niet toegekend*
Dit begrip is gekoppeld aan de volgende thema(s):
  • Management (management) >> Managen (to manage) >> Plannen (to plan)
  • Management (management) >> * - management >> Projectmanagement (project management) >> Tijd (time)

Verder zoeken naar logisch verband

Selecteer hieronder het begrip in de taal waarin u verder wil zoeken. Vervolgens verschijnen de beschikbare zoekvragen voor die taal.

     logisch verband
     logical relationship
Algemeen
(20)
Literatuur
(28)
Lessen
(9)
Gereedschap
(6)
Multimedia
(21)
De praktijk
(13)
Algemeen
(15)
Literatuur
(18)
Lessen
(7)
Gereedschap
(6)
Multimedia
(17)
De praktijk
(14)

Heeft u opmerkingen/suggesties omtrent dit begrip? Klik hier om deze door te geven.