- latest start
- latest start
The latest day that a work item can start without affecting the final project
duration. This assumes that it is completed in its expected time and all
subsequent work items start as soon as they are able and are completed in their
expected times.
Source: Max Wideman.com
Copyright: Wideman Comparative Glossary
of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March
2002.