- discontinuous activity
- discontinuous activity
An activity in which the interval between the start and finish dates is allowed
to exceed its duration in order to satisfy start-to-start and finish-to-finish
relationships with other activities.
Source: Max Wideman.com
Copyright: Wideman Comparative Glossary
of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March
2002.