- arrow diagramming
- arrow diagramming
Een techniek om de opeenvolging van gebeurtenissen en/of activiteiten en hun onderlinge relaties in kaart te brengen.
Bron: Kennisconsult
A technique that may be used in both CPM and PERT to display the network
sequence and timing of activities. The technique is event oriented in that the
connecting arrows represent the activities. It is simple to understand and
display straight forward networks. Its flexibility is limited in comparison with
precedence diagramming.
Source: Max Wideman.com
Copyright: Wideman Comparative Glossary
of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March
2002.