finish-to-start-uitstel

 - finish-to-start-uitstel
 - finish-to-start-lag


De minimumhoeveelheid tijd die moet liggen tussen het einde van de ene activiteit en het begin van de vervolgactiviteit.
Bron: Kennisconsult


The minimum amount of time that must pass between the finish of one activity and the start of its successor(s). The default finish-to-start lag is zero. All lags are calculated when a project has its schedule computed. In most cases, Finish-to-Start lags are not used with other lag types.
Source: Max Wideman.com
Copyright: Wideman Comparative Glossary of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March 2002.

Kennisconsult
Laatst bijgewerkt: 21-06-2012
Thema: projectmatig werken
Dit begrip is gekoppeld aan de volgende thema(s):
  • Management (management) >> Managen (to manage) >> Plannen (to plan)
  • Management (management) >> * - management >> Projectmanagement (project management) >> Tijd (time)
Gerelateerde begrippen:

Verder zoeken naar finish-to-start-uitstel

Selecteer hieronder het begrip in de taal waarin u verder wil zoeken. Vervolgens verschijnen de beschikbare zoekvragen voor die taal.

     finish-to-start-uitstel
     finish-to-start-lag
Algemeen
(20)
Literatuur
(28)
Lessen
(9)
Gereedschap
(6)
Multimedia
(21)
De praktijk
(13)
Algemeen
(15)
Literatuur
(18)
Lessen
(7)
Gereedschap
(6)
Multimedia
(17)
De praktijk
(14)

Heeft u opmerkingen/suggesties omtrent dit begrip? Klik hier om deze door te geven.